- 07월 28일
- 07월 29일
- 07월 30일
- 07월 31일
- 08월 01일![20140801_090802.jpg](/xe/files/attach/images/832/689/010/e93e25fb3168666aa535bb66b7ea491e.jpg)
![20140728_164036.jpg](/xe/files/attach/images/832/689/010/8037179821b5707ee4e154acdd96c3fb.jpg)
![20140728_171550.jpg](/xe/files/attach/images/832/689/010/823553389177767a5949b0609056e922.jpg)
![20140729_164748.jpg](/xe/files/attach/images/832/689/010/4fb569233109404d93b4d8e4fb316b5a.jpg)
![20140729_094038.jpg](/xe/files/attach/images/832/689/010/5933d9b52d6fa54a0c0635a13c3cb84e.jpg)
![20140730_170924.jpg](/xe/files/attach/images/832/689/010/cca1eed30cdb28ef2bcbbcb4e0b40ed4.jpg)
![20140730_092636.jpg](/xe/files/attach/images/832/689/010/01ad38fd0457c7f12b93fb3bffb09fef.jpg)
![20140731_193729.jpg](/xe/files/attach/images/832/689/010/af17480c68b6b6c6ed73eddbe54077ed.jpg)
![20140731_092026.jpg](/xe/files/attach/images/832/689/010/b6eb92ea256ea89486425137469535de.jpg)
![20140731_1937153.jpg](/xe/files/attach/images/832/689/010/daa5997f622b3d87ee2216e8ba4c5cee.jpg)
![20140801_090802.jpg](/xe/files/attach/images/832/689/010/e93e25fb3168666aa535bb66b7ea491e.jpg)
댓글 1
-
문성희
2014.08.06 15:00
공사일지 | 2014년 07월 28일 ~ 08월 02일07/28(월) 지상9층 슬래브 합판 거푸집 설치, 지상층 객실 시멘트 벽돌 쌓기07/29(화) 지상9층 슬래브 철근배근, 지상8층 동측 옹벽 철근배근 및 거푸집 설치, 지상4층 설비 배관 기초 작업, 지하2층 4인치 블럭쌓기 및 지상층 시멘트 벽돌 쌓기, 지상9층 슬래브 전기 및 통신 박스 매입 및 주름관 배관, 지하1층 방수턱 방수 치켜올림07/30(수) 지상9층 슬래브 철근배근, 지상8층 옹벽 및 지상9층 슬래브 잔손보기, 지상9층 슬래브 위생설비 슬리브 매입, 지상층 객실 시멘트 벽돌 쌓기, 지상9층 슬래브 전기 및 통신 박스 매입 및 주름관 배관07/31(목) 지상9층 슬래브 콘크리트 타설, 지상층 위생설비 배관, 지상층 객실 시멘트 벽돌 쌓기, 주계단실 통신 트레이 설치08/01(금) 지상8층 옹벽 거푸집 해체, 지상층 객실 시멘트벽돌 쌓기08/02(토) 태풍 나크리 대비 현장 안전관리